Projects

Karakaya Dam & HEPP (8x300 MW)

Diyarbakır / Turkey

CLIENT: General Directorate of State Hydraulic Works (DSİ) of Turkey

PROJECT: KARAKAYA DAM AND HEPP (6x300 MW), ÇÜNGÜŞ-DIYARBAKIR / TURKEY

CONTRACTOR: Italstrade-Recchi Spa / Italy

SUB-CONTRACTOR: Noell GmbH and Çiltuğ Joint Venture

SCOPE:

  • Fabrication, sandblasting, painting and erection of all permanent hydro-mechanical equipment such of Penstocks
  • Penstocks: Ø6 m L= 80 mx6 lines, 5,500 tons Spillway radial gates: 14 mx10 m, 1,500 tons Water intake equipment: 2,700 tons
  • Bottom outlet tunnel steel lining and gates: 3,250 tons Draft tube gates: 650 tons
  • Power house machine hall cranes and other cranes erections: 1,900 tons.

TOTAL WEIGHT: 15,500 Tons

COMPLETED IN: 1989